History
At the Brigittenau spur, where the Danube Canal branches off from the main stream, the floating gate of the engineer Wilhelm von Engerth protected the city from ice jams from 1873. It was hung across the canal when danger threatened, but could hardly be regulated. When the city planned the Stadtbahn, collector sewers and a harbour on the Danube Canal, it was no longer enough.
From 1894 to 1899 the weir and lock complex was therefore built. Otto Wagner, as artistic adviser, drew up the plans for the architecture of the weir with the Schemerl Bridge and the ancillary buildings, while the technical planning came from Siegmund Taussig. The masonry was finished in 1897, and in 1898 the firm Albert Milde installed the steel structure. The weir passed its first test in the flood of 1899.
The Lion Bridge carries the name of Joseph Schemerl von Leythenbach, who had drawn up an unrealised Danube regulation project in 1810. Its two bronze lions were made by Rudolf Weyr.
From 1971 to 1975 a modern segment weir replaced the needle weir. Between 2004 and 2005 the Nussdorf power plant was built beneath it without altering the historic overall appearance. Since 2017 the Vienna waters authority MA 45 has had its headquarters in Otto Wagner’s lock building.