History
The Klinik Floridsdorf of the Vienna Health Association was called Krankenhaus Nord until 2020 and is one of the city's youngest hospitals. It took over the duties of the hospital in Hinaysgasse, which operated until 2019.
It was built on about 111,000 square metres at Brünner Straße, where the ÖBB main workshop Floridsdorf had stood. From October 2010 the area was cleared, and in eight months about 80,000 tonnes of concrete and 14,000 tonnes of brick were removed. The architectural competition in December 2008 was won by the Viennese architect Albert Wimmer among more than 30 participating practices. The foundation stone was laid on 18 September 2012.
On 6 April 2019 the clinic could be visited on an open day, and test operation began on 8 April. Regular operation followed in June 2019, and full operation has run since September 2019.
The building became far more expensive than planned: 825 million euros had been estimated, at the end of 2017 at least 1.3 billion euros became known, and the estimate of March 2018 was 1.6 billion.