History
The Kraftwerk Graz-Puntigam dams the Mur in the south of Graz, about 600 metres upstream of the Puntigamer Brücke. The raised water level meant that embankments had to be piled up. At the plant they are more than three metres high, and they are meant to become lower further upstream. A path 3.2 metres wide for pedestrians and cyclists leads across the plant. It opened on 12 July 2022.
First concrete plans date from 2009, and construction began in January 2017. In June 2019 the turbines went into partial trial operation, and on 9 October 2019 the plant started regular operation. It has an installed capacity of 17.7 megawatts and is meant to generate 82 gigawatt hours of electricity a year. Energie Steiermark runs the plant. The construction cost is reportedly about 80 million euros.
On the Mur it lies between two older plants: the Weinzödl plant, in operation since 1982, is 9 kilometres upstream, and the Gössendorf plant, in operation since 2012, is 5 kilometres downstream. Residents voiced concerns about the project early on. Conservationists criticised that spawning grounds and fish habitats would be lost, and the figures for the number of trees to be felled differed widely. In September 2016 a citizens' initiative submitted signatures for a referendum, and the city council rejected the demand. After the clearing began in February 2017, activists occupied the site several times.